Thursday, May 11, 2017

Factors affecting performance and capacity in Project Server 2013

Entity Description/Notes Small Medium Large
Projects   20 100 5000
Project Sites   20 100 5000
% Projects in Managed Mode   0% 10% 80%
Tasks   1250 25000 1250000
Average Tasks Per Project   62.5 250 250
Task Transaction History The number of times status tends to be submitted and approved for any given task 10 10 100
Assignments   1625 32500 1625000
Average Assignments Per Task   1.3 1.3 1.3
Average Tasks per My Site User   50 250 5000
Approvals Pending updates per manager 5 50 600
Resources   50 1000 10000
Average Resources Per Project   2.5 10 20
Average Assignments Per Resource   32.5 32.5 162.5
Users   50 1000 10000
Calendars   3 26 100
Issues   20 400 20000
Risks   20 400 20000
Deliverables   20 800 40000
Enterprise Project Types     5 50
Workflows     2 30
Average Projects Per Workflow     50 167
Phases     5 50
Phases Per Enterprise Project Type     20 20
Stages     15 150
Stages Per Workflow     20 40
PDPs     10 100
Custom Fields Per PDP     10 10
Number of Departments       100
Average Projects Per Department       50
Average Resources Per Department       100
Timesheets Per Year The more you utilize timesheets, the more resource demands will be placed on SQL Server. 2600 52000 780000
Status Reports Per Year     26000 260000